Supply Chain Notice
May 27, 2010

The following notice was sent to all buyers of Eurotech products. Key points are the following:

- Due to increasing lead times on components, we are changing our order lead time to 20 weeks.
- Eurotech Inc cannot accept changes to orders within 16 weeks of a scheduled shipment.
- We are transitioning to blue circuit boards. Orders may have a mix of colors during the transition.

PDF (126 kB)